2025 Water Main Improvements to Begin Starting the Week of Oct. 27
Weather Permitting
- October 27-31 mobilization, project start-up, street milling
- November 3-11 E Logan Street from East Street to Czacki Street installation
- November 17-December 1 Forest Lane from Keepataw Drive to Cul-de-sac installation
- December 3-12 Keepataw Lane from Keepataw Drive to Cul-de-sac installation
Please be alert and watch for road signs, construction workers and changing road conditions.